refactor workday code
git-svn-id: https://svn.apache.org/repos/asf/poi/trunk@1897952 13f79535-47bb-0310-9956-ffa450edef68
This commit is contained in:
parent
27366a22a2
commit
9c55c8d456
|
@ -20,7 +20,9 @@ package org.apache.poi.ss.formula.atp;
|
|||
import java.util.Arrays;
|
||||
import java.util.Calendar;
|
||||
import java.util.Date;
|
||||
import java.util.HashMap;
|
||||
import java.util.HashSet;
|
||||
import java.util.Map;
|
||||
import java.util.Set;
|
||||
|
||||
import org.apache.poi.ss.usermodel.DateUtil;
|
||||
|
@ -61,6 +63,24 @@ public class WorkdayCalculator {
|
|||
new HashSet<>(Arrays.asList(new Integer[]{Calendar.SATURDAY}));
|
||||
private static final Set<Integer> sunWeekend =
|
||||
new HashSet<>(Arrays.asList(new Integer[]{Calendar.SUNDAY}));
|
||||
private static final Map<Integer, Set<Integer>> weekendTypeMap = new HashMap<>();
|
||||
|
||||
static {
|
||||
weekendTypeMap.put(1, standardWeekend);
|
||||
weekendTypeMap.put(2, sunMonWeekend);
|
||||
weekendTypeMap.put(3, monTuesWeekend);
|
||||
weekendTypeMap.put(4, tuesWedsWeekend);
|
||||
weekendTypeMap.put(5, wedsThursWeekend);
|
||||
weekendTypeMap.put(6, thursFriWeekend);
|
||||
weekendTypeMap.put(7, friSatWeekend);
|
||||
weekendTypeMap.put(11, monWeekend);
|
||||
weekendTypeMap.put(12, tuesWeekend);
|
||||
weekendTypeMap.put(13, wedsWeekend);
|
||||
weekendTypeMap.put(14, thursWeekend);
|
||||
weekendTypeMap.put(15, friWeekend);
|
||||
weekendTypeMap.put(16, satWeekend);
|
||||
weekendTypeMap.put(17, sunWeekend);
|
||||
}
|
||||
|
||||
/**
|
||||
* Constructor.
|
||||
|
@ -88,6 +108,7 @@ public class WorkdayCalculator {
|
|||
|
||||
/**
|
||||
* Calculate the workday past x workdays from a starting date, considering a range of holidays.
|
||||
* Uses Sat/Sun weekend.
|
||||
*
|
||||
* @param start start date.
|
||||
* @param workdays number of workdays to be past from starting date.
|
||||
|
@ -95,6 +116,20 @@ public class WorkdayCalculator {
|
|||
* @return date past x workdays.
|
||||
*/
|
||||
public Date calculateWorkdays(double start, int workdays, double[] holidays) {
|
||||
return calculateWorkdays(start, workdays, 1, holidays);
|
||||
}
|
||||
|
||||
/**
|
||||
* Calculate the workday past x workdays from a starting date, considering a range of holidays.
|
||||
*
|
||||
* @param start start date.
|
||||
* @param workdays number of workdays to be past from starting date.
|
||||
* @param weekendType weekend parameter (see https://support.microsoft.com/en-us/office/workday-intl-function-a378391c-9ba7-4678-8a39-39611a9bf81d)
|
||||
* @param holidays an array of holidays.
|
||||
* @return date past x workdays.
|
||||
*/
|
||||
public Date calculateWorkdays(double start, int workdays, int weekendType, double[] holidays) {
|
||||
Set<Integer> weekendDays = weekendTypeMap.getOrDefault(weekendType, standardWeekend);
|
||||
Date startDate = DateUtil.getJavaDate(start);
|
||||
int direction = workdays < 0 ? -1 : 1;
|
||||
Calendar endDate = LocaleUtil.getLocaleCalendar();
|
||||
|
@ -103,7 +138,7 @@ public class WorkdayCalculator {
|
|||
while (workdays != 0) {
|
||||
endDate.add(Calendar.DAY_OF_YEAR, direction);
|
||||
excelEndDate += direction;
|
||||
if (!isWeekend(endDate) && !isHoliday(excelEndDate, holidays)) {
|
||||
if (!isWeekend(endDate, weekendDays) && !isHoliday(excelEndDate, holidays)) {
|
||||
workdays -= direction;
|
||||
}
|
||||
}
|
||||
|
|